It’s been a month since we received our Planning Permit from Kingborough Council, but sadly this didn’t give us the right to actually do anything. Possession of a Planning Permit merely confers upon us the right to apply for a Permit To Build. Until we receive that second document, we can’t even break ground on our land.
Time is ticking on, and Council is still sitting on our Permit to Build. Without that document, we not only can’t build, but we can’t get a loan. The bank are patiently sitting on our loan application, but we’ve already had to ‘refresh’ our loan paperwork once already, when the bank statements and so on that we’d provided went out of date. It is frustrating because we’re still making substantial payments to Get Things Done, and our cash reserves are dwindling. In addition, part of our contracted agreement is that the foundations must be “substantially completed” by early November, and it’s now late October and we can’t get them started.
If we’d been building in the traditional manner, on concrete foundations at our property, we’d now be up the proverbial creek, with no way of getting the build done in time. We are, after all, moving to Tasmania in December.
Luckily, the house is being built off-site as two separate wings in TasBuilt‘s factory, and we had enough cash to get them started with the framing and windows, so they forged right ahead and started building. The framing was done in a couple of days.
Despite the fact that we can’t pay the builders any more money until our loan goes through, their factory has its own timetable and they were keen to continue; a week later they’d installed the windows, electrics, and made a start on the insulation.
Electrics in the living wing (Oct 10) External wall insulation to the front of the house (Oct 10) Internal wall insulation in one of the bedrooms (Oct 10)
A week later, they’d made a start on the roof and cladding, and made good progress on the dry-walling.
Dry-walling in the living wing. It looks nice and bright! (Oct 17) Cladding and roof detail on the back of the service wing (Oct 17) Ensuite and walk-in wardrobe from the master bedroom
Now that the builders have started, it seems that nothing can stop them. The house is due to be completed and moved to our property (on two low-loaders in the middle of the night) in a fortnight’s time. Before it arrives, the foundation posts need to be in place. These are scheduled to go in next Wednesday… and we’re still waiting for the Permit to Build.